MAS Dynamics · Türkiye-based EDGE Expert & Approved EDGE Auditor team WhatsApp · [email protected] · Türkçe

EDGE Certification for SHIFA Project Contractors

We complete the EDGE certification requirement in EU-funded SHIFA health centre construction, run by the Ministry of Health and CEB, in line with your progress payment and acceptance schedule.

What is the SHIFA Project?

SHIFA – Strengthening Health Infrastructure for All is a health infrastructure programme financed by the European Union and run by the Ministry of Health of the Republic of Türkiye with the support of the Council of Europe Development Bank (CEB). Under the programme, about 60 new health centres (ASM/GSM/GGSM) are being built in more than 20 provinces, 23 health centres are being renovated and hospital physiotherapy units are being set up. Implementation runs until the end of 2027.

Where does the EDGE requirement come from?

In health centre construction works under SHIFA, the project and technical specification require the buildings to obtain IFC EDGE green building certification. The certificate is obtained by the contractor and is part of the acceptance process. Completed SHIFA health centres are published in the EDGE App with the "Ministry of Health of Türkiye" as client, mostly at the EDGE Advanced level.

SHIFA and EDGE in brief

  • Financing: EU (IPA) funding; run by the Ministry of Health of Türkiye and the Council of Europe Development Bank (CEB)
  • Scope: about 60 new health centres, 23 renovations and 1 hospital in 23 provinces; until the end of 2027
  • Building types: family health centre (ASM), migrant health centre (GSM / GGSM), health centre
  • Certificate: Final EDGE certificate; issued by GBCI, an independent EDGE Auditor audit is mandatory

When you work with us we run the entire EDGE process from contract to final certificate; consulting and audit in the same team, in a single contract.

Timing warning: SHIFA projects have no separate design (preliminary) certification stage; they go directly to the final certificate. The final certificate must be delivered before provisional acceptance. The site audit appointment and GBCI review time (about 4 weeks) should be planned in the acceptance schedule in advance.
SHIFA health centres we have completed

Final EDGE certificates for the Ministry of Health

ProjectTypeLevelEnergyWaterMaterialsArea (m²)ClientLocation
Batman Çarşı Health Centre
Final certificate · 2026-10
Health CentreEDGE Certified28%74%40%878Ministry of Health of TürkiyeBatman
Adıyaman Merkez ASM-GGSM
Final certificate · 2026-10
Health CentreEDGE Certified39%57%30%1.109Ministry of Health of TürkiyeAdıyaman
Süleymaniye 4+4 GSM Building
Final certificate · 2026-09
Health CentreEDGE Advanced57%57%33%1.104Ministry of Health of TürkiyeBursa (İnegöl)
Selçuklu No. 66 Campus Family Health Centre
Final certificate · 2026-07
Health CentreEDGE Advanced43%75%32%1.189Ministry of Health of TürkiyeKonya
Şanlıurfa Birecik No. 1 Family Health Centre
Final certificate · 2026-05
Health CentreEDGE Advanced52%66%43%2.637Ministry of Health of TürkiyeŞanlıurfa
Şanlıurfa Karaköprü No. 1 Family Health Centre
Final certificate · 2026-05
Health CentreEDGE Advanced47%73%36%1.081Ministry of Health of TürkiyeŞanlıurfa
Mersin Nusratiye Family Health Centre (İhsaniye)
Final certificate · 2026-05
Health CentreEDGE Advanced41%72%39%1.340Ministry of Health of TürkiyeMersin
Mersin Gündoğdu Family Health Centre
Final certificate · 2026-05
Health CentreEDGE Advanced44%51%48%1.013Ministry of Health of TürkiyeMersin

Source: IFC EDGE App project records. EDGE Auditor: Mehmet Okumuş · EDGE Expert (consultant): MAS Dynamics.

Typical EDGE measures in health centres

Energy (for ≥40%)

External wall/roof insulation, glazing with low U and SHGC values, VRF or heat pump, heat-recovery ventilation, LED lighting and sensors, efficient hot water system, rooftop PV.

Water (≥20%)

Low-flow basin taps (≤6 l/min), dual-flush cistern (≤4.5/3 l), efficient urinals, kitchen taps; rainwater storage where possible.

Materials (≥20%)

Lightweight floor systems, locally produced brick/AAC, steel with recycled content, suitable window frame and insulation choices.

Full article: EDGE for healthcare buildings →

Talk to us about your project

Every project is assessed individually. Write to us on WhatsApp or by email; let's review your project together.

  [email protected]